as of 17 July 2024, 1:30PM
Yellow Alert
3:00PM-9:00PM
ใฝ๏ธAvailable Capacity- 13,198MW
ใฝ๏ธPeak Demand- 12,028MW
ใฝ๏ธ1 plant has been on forced outage since 2023, 8 between January and May 2024, and 6 power plants between June and July 2024; while 6 are running on derated capacities, for a total of 1,652.7MW unavailable to the grid.
Factor that contributed to the raising of yellow alert:
ใฝ๏ธTripping of San Gabriel (417.4MW)
The Visayas and Mindanao grids are under normal condition.
A Yellow Alert is issued when the operating margin is insufficient to meet the transmission gridโs contingency requirement.